Essay
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
Correct Answer:

Verified
(a)crash cost X = $1,000 per d...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q3: In project management, crashing an activity must
Q7: Pirmin's Bike Shop is behind on a
Q9: A contractor's project being analyzed by PERT
Q14: Which of the following is NOT a
Q18: What are some of the ethical issues
Q28: What is a project organization?
Q30: What are the three phases of a
Q31: A simple CPM network has three activities,A,B,and
Q78: The time an activity will take assuming
Q93: Which of the following statements regarding PERT