Multiple Choice
The time an activity will take assuming very unfavorable conditions is:
A) the optimistic time.
B) the pessimistic time.
C) the activity variance.
D) the minimum time.
E) exactly twice as long as the expected time.
Correct Answer:

Verified
Correct Answer:
Verified