In a PERT network, the earliest (activity) start time is the
A) earliest time that an activity can be finished without delaying the entire project.
B) latest time that an activity can be started without delaying the entire project.
C) earliest time that an activity can start without violation of precedence requirements.
D) latest time that an activity can be finished without delaying the entire project.
Correct Answer:

Verified
Correct Answer:
Verified
Q41: Given (Time in weeks):<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Given
Q42: In a PERT analysis, how is the
Q43: The expected time in PERT is<br>A)a weighted
Q44: The three time estimates employed in PERT
Q45: Which of the following is not a
Q47: Table 11-7<br>A project manager calculated early and
Q48: Table 11-9<br>A mad scientist has identified the
Q49: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="The
Q50: Table 11-8<br>A mad scientist has identified the
Q51: In PERT analysis, how is the pessimistic