Multiple Choice
Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.These costs are easy to quantify, but it's difficult to stomach not controlling the world when it's just a matter of a few extra dollars.What's the cost of the minimum duration project?
A) $158,550
B) $163,850
C) $156,350
D) $161,550
Correct Answer:

Verified
Correct Answer:
Verified
Q45: Which of the following is not a
Q46: In a PERT network, the earliest (activity)start
Q47: Table 11-7<br>A project manager calculated early and
Q48: Table 11-9<br>A mad scientist has identified the
Q49: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="The
Q51: In PERT analysis, how is the pessimistic
Q52: Table 11-8<br>A mad scientist has identified the
Q53: PERT is a deterministic analysis tool allowing
Q54: Given an activity's optimistic, most likely, and
Q55: Table 11-6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-6