Multiple Choice
CPM
A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Budgets are computed using only ES times.
Q6: In PERT, the earliest start time for
Q7: For projects that have a daily fixed
Q8: Slack time in a network is the<br>A)amount
Q9: An IT project requires 6 activities.The table
Q11: In PERT, we assume that<br>A)the times to
Q12: Table 11-9<br>A mad scientist has identified the
Q13: Given the following small project, the critical
Q14: A small software development project has five
Q15: Development of a new deluxe version of