Solved

CPM

Question 10

Multiple Choice

CPM


A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.

Correct Answer:

verifed

Verified

Unlock this answer now