Multiple Choice
Slack time in a network is the
A) amount of time that an activity would take assuming very unfavorable conditions.
B) shortest amount of time that could be required to complete the activity.
C) amount of time that you would expect it would take to complete the activity.
D) amount of time that an activity can be delayed without delaying the entire project.
Correct Answer:

Verified
Correct Answer:
Verified