    Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates
Solved

Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates

Question 117

Question 117

Multiple Choice

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity.


A) 2.33
B) 5.44
C) 8.00
D) 64.00

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q112: In a PERT network, the latest (activity)start

Q113: PERT assumes that the total completion time

Q114: One PERT/COST assumption is that money is

Q115: Your company is considering submitting a bid

Q116: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1

Q118: An IT project requires 6 activities.The table

Q119: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3

Q120: Table 11-2<br>The following represents a project with

Q121: Table 11-4<br>The following represents a project with

Q122: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines