Multiple Choice
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time.What due date should be set?
A) 108.0
B) 160.4
C) 166.5
D) 135.0
Correct Answer:

Verified
Correct Answer:
Verified
Q110: In PERT analysis, the probability of the
Q111: Table 11-8<br>A mad scientist has identified the
Q112: In a PERT network, the latest (activity)start
Q113: PERT assumes that the total completion time
Q114: One PERT/COST assumption is that money is
Q116: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1
Q117: Given an activity's optimistic, most likely, and
Q118: An IT project requires 6 activities.The table
Q119: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3
Q120: Table 11-2<br>The following represents a project with