Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively, compute the expected time for this activity.
A) 5
B) 6
C) 7
D) 12
Correct Answer:

Verified
Correct Answer:
Verified