    Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates
Solved

Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates

Question 18

Question 18

Multiple Choice

Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively, compute the expected time for this activity.


A) 5
B) 6
C) 7
D) 12

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: Given the following small project, the critical

Q14: A small software development project has five

Q15: Development of a new deluxe version of

Q16: Table 11-5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-5

Q17: Reducing the overall activity time is based

Q19: Table 11-4<br>The following represents a project with

Q20: An IT project requires 6 activities.The table

Q21: Which of the following statements about project

Q22: Consider the tasks, durations, and predecessor relationships

Q23: Given the following small project, the critical

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines