Which of the following statements about project crashing is false?
A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: Table 11-5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-5
Q17: Reducing the overall activity time is based
Q18: Given an activity's optimistic, most likely, and
Q19: Table 11-4<br>The following represents a project with
Q20: An IT project requires 6 activities.The table
Q22: Consider the tasks, durations, and predecessor relationships
Q23: Given the following small project, the critical
Q24: PERT stands for<br>A)probabilistic evaluation and review technique.<br>B)program
Q25: Table 11-8<br>A mad scientist has identified the
Q26: The first step in planning and scheduling