Which of the Following Statements About Project Crashing Is False

Question 21

Multiple Choice

Which of the following statements about project crashing is false?


A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.