menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management
  4. Exam
    Exam 11: Project Management
  5. Question
    Activity B of a Project Has a Budgeted Cost of $50,000
Solved

Activity B of a Project Has a Budgeted Cost of $50,000

Question 109

Question 109

Multiple Choice

Activity B of a project has a budgeted cost of $50,000 and is 30% complete.The actual cost of the activity is $12,000.What is the activity difference?


A) -15,000
B) -3,000
C) 0
D) 3,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q104: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1

Q105: PERT and CPM are quantitative analysis tools

Q106: Table 11-1<br>The following represents a project with

Q107: Table 11-7<br>A project manager calculated early and

Q108: The two common techniques for drawing PERT

Q110: In PERT analysis, the probability of the

Q111: Table 11-8<br>A mad scientist has identified the

Q112: In a PERT network, the latest (activity)start

Q113: PERT assumes that the total completion time

Q114: One PERT/COST assumption is that money is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines