Activity B of a project has a budgeted cost of $50,000 and is 30% complete.The actual cost of the activity is $12,000.What is the activity difference?
A) -15,000
B) -3,000
C) 0
D) 3,000
Correct Answer:

Verified
Correct Answer:
Verified