Solved

Table 11-7 A Project Manager Calculated Early and Late Start and Finish

Question 107

Multiple Choice

Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.
Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries.The remaining legible entries are correct.    -Consider the project summarized in Table 11-7.What is the critical path? A) ABDGH B) ACEGH C) ABDFH D) ACEFH
-Consider the project summarized in Table 11-7.What is the critical path?


A) ABDGH
B) ACEGH
C) ABDFH
D) ACEFH

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions