Multiple Choice
Which of these statements is best?
A) Slack is the time an activity can be delayed without impacting the completion time of the project.
B) The variance of the project completion time is equal to the sum of the variances of all the activities.
C) In PERT, we assume that the project completion time can be modeled by the beta distribution.
D) In PERT, the variance in completion time is equal to the variance of the most time-consuming activity on the critical path.
Correct Answer:

Verified
Correct Answer:
Verified
Q122: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1
Q123: The optimistic time is the greatest amount
Q124: The activity crash cost is equal to
Q125: The activity difference is the actual duration
Q126: Development of a new deluxe version of
Q128: The critical path of a network is
Q129: Given an activity's optimistic, most likely, and
Q130: Table 11-8<br>A mad scientist has identified the
Q131: Given the variability of the activity completion
Q132: Given an activity's optimistic, most likely, and