Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
Correct Answer:

Verified
Correct Answer:
Verified
Q127: Which of these statements is best?<br>A)Slack is
Q128: The critical path of a network is
Q129: Given an activity's optimistic, most likely, and
Q130: Table 11-8<br>A mad scientist has identified the
Q131: Given the variability of the activity completion
Q133: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1
Q134: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3
Q135: In CPM, crashing an activity that is
Q136: Given an activity's optimistic, most likely, and
Q137: Activity C of a project has a