Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 2,5,and 14 days respectively,compute the PERT expected activity time for this activity.
A) 6
B) 7
C) 9
D) 5
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified