menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management Study Set 2
  4. Exam
    Exam 11: Project Management
  5. Question
    Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 3,6,and
Solved

Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 3,6,and

Question 60

Question 60

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 3,6,and 9 days respectively,compute the PERT variance for this activity.


A) 3
B) 1
C) 9
D) 6
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q51: In PERT analysis, how is the pessimistic

Q55: Given an activity's optimistic,most likely,and pessimistic time

Q56: Before drawing a PERT or CPM network,

Q56: The two common techniques for drawing PERT

Q59: An IT project requires 6 activities.The table

Q61: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6

Q62: Slack time in a network is the<br>A)amount

Q63: Slack is the time an activity can

Q64: Which of the following is not a

Q65: Table 11-5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-5

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines