Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,6,and 9 days respectively,compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified