Multiple Choice
Table 12-2
The following represents a project with four activities. All times are in weeks.
-According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)
A) 0.07
B) 0.93
C) 0.43
D) 0.77
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Given an activity's optimistic,most likely,and pessimistic time
Q76: Managers use the network analysis of PERT
Q79: Figure 12-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2951/.jpg" alt="Figure 12-1
Q80: Table 12-4<br>The following represents a project with
Q85: Table 12-2<br>The following represents a project with
Q86: Table 12-1<br>The following represents a project with
Q87: Figure 12-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2951/.jpg" alt="Figure 12-1
Q88: Figure 12-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2951/.jpg" alt="Figure 12-1
Q94: In PERT,we assume that the project completion
Q105: PERT and CPM are quantitative analysis tools