Multiple Choice
Figure 12-1
-Given the network in Figure 12-1, the critical path is
A) A-C-F-H.
B) B-D-E-F-H.
C) A-C-E-G-H.
D) B-D-G-E-F-H.
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified