Multiple Choice
The two common techniques for drawing PERT networks are
A) NOA and NRA.
B) AON and AOA.
C) GANTT and NOA.
D) ONA and OAO.
E) CAN and CAA.
Correct Answer:

Verified
Correct Answer:
Verified