menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management Study Set 1
  4. Exam
    Exam 12: Project Management
  5. Question
    Table 12-4 The Following Represents a Project with Known Activity Times. All
Solved

Table 12-4 The Following Represents a Project with Known Activity Times. All

Question 66

Question 66

Multiple Choice

Table 12-4
The following represents a project with known activity times. All times are in weeks. Table 12-4 The following represents a project with known activity times. All times are in weeks.   -Using the data in Table 12-4, compute the slack time for activity D. A)  0 B)  5 C)  3 D)  6 E)  None of the above
-Using the data in Table 12-4, compute the slack time for activity D.


A) 0
B) 5
C) 3
D) 6
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q37: Given an activity's optimistic,most likely,and pessimistic time

Q45: The expected completion time and variance of

Q67: Which of the following statement about project

Q68: Table 12-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2951/.jpg" alt="Table 12-6

Q70: Development of a new deluxe version of

Q83: The critical path of a network is

Q90: PERT<br>A)assumes that we do not know ahead

Q96: Your company is considering submitting a bid

Q123: The optimistic time is the greatest amount

Q142: The identification of the project activities and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines