Your company is considering submitting a bid on a major project.You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time.What due date should be set?
A) 108.0
B) 160.4
C) 166.5
D) 135.0
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q91: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1
Q92: Table 11-4<br>The following represents a project with
Q93: PERT stands for<br>A)probabilistic evaluation and review technique.<br>B)program
Q94: In PERT,we assume that the project completion
Q95: The first step in planning and scheduling
Q97: Table 11-4<br>The following represents a project with
Q98: Consider the tasks,durations,and predecessor relationships in the
Q99: The variance of the project completion time
Q100: CPM stands for Comprehensive Project Method.
Q101: Table 11-2<br>The following represents a project with