Multiple Choice
Table 8-4
The following is a linear programming formulation of a labor planning problem. There are four overlapping shifts, and management must decide how many employees to schedule to start work on each shift. The objective is to minimize the total number of employees required while the constraints stipulate how many employees are required at each time of day. The variables X1 - X4 represent the number of employees starting work on each shift (shift 1 through shift 4) .
-According to Table 8-4, which describes a labor planning problem and its solution, how many workers would be assigned to shift 1?
A) 12
B) 13
C) 0
D) 2
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q1: In production scheduling LP problems,inventory at the
Q7: Ivana Miracle wishes to invest her full
Q7: The linear programming model of the production
Q10: Table 8-5<br>Ivana Myrocle wishes to invest her
Q13: Table 8-3<br>Each coffee table produced by Timothy
Q14: Table 8-3<br>Each coffee table produced by Timothy
Q16: Table 8-3<br>Each coffee table produced by Timothy
Q31: What is another name for blending problems?<br>A)diet
Q34: Swearingen and McDonald, a small furniture manufacturer,
Q82: Describe the portfolio selection linear programming application.