The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks.
(a) What is the probability that the project is finished in 40 weeks or fewer?
(b) What is the probability that the project is finished in 52 weeks or fewer?
(c) There is an 95 percent chance that the project will be finished in fewer than how many weeks?
Correct Answer:

Verified
(a) 0.3085...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q14: If the sale of ice cream and
Q15: The Department of Motor Vehicles (DMV)can service
Q38: The number of cars passing through an
Q48: Properties of the normal distribution include<br>A)a continuous
Q52: In what way is the F distribution
Q71: In a given office, the color printer
Q118: The time required to complete a project
Q119: Suppose that 10 golfers enter a tournament
Q122: Suppose that you enter a drawing by
Q141: Assume that you have an urn containing