This meeting is held when the contractor has completed the initial conceptual specifications, drawings, or flowcharts.
A) A status review meeting
B) A detailed design review meeting
C) A preliminary design review meeting
D) A final design review meeting
Correct Answer:

Verified
Correct Answer:
Verified