Multiple Choice
The purpose of this meeting is to gain approval from the customer before the contractor orders materials that have a long delivery time (so as not to delay the project schedule) .
A) A status review meeting
B) A detailed design review meeting
C) A preliminary design review meeting
D) A final design review meeting
Correct Answer:

Verified
Correct Answer:
Verified