Multiple Choice
The process of closing the project involves various actions, including
A) identifying which resources to use for the project.
B) collecting and making final payments.
C) adding in extra work if the project hasn't spent all the funds.
D) replenishing office supplies that may not have been used on the project.
Correct Answer:

Verified
Correct Answer:
Verified