Participants of ____ Should Include the Project Manager, Key Project

Question 11

Multiple Choice

Participants of ____ should include the project manager, key project team members, and key representatives of the customer's organization who were involved with the project.


A) a post-project evaluation meeting with the customer or sponsor
B) a project progress meeting with project stakeholders
C) an analysis session with the project team
D) a pre-RFP meeting with the customer