Solved

Which of the Following Is the Most Likely the Short-Term

Question 14

Multiple Choice

Which of the following is the most likely the short-term result of a project being terminated early by a customer?


A) The contractor experiences a financial loss and may have to lay off employees.
B) The contractor's reputation is tarnished.
C) There will be no future business from the customer.
D) Other businesses withdraw their future projects from the contractor.