Solved

A Method for Calculating the Forecasted Cost at Completion Assumes

Question 6

Multiple Choice

A method for calculating the forecasted cost at completion assumes that the work to be performed on the remaining portion of the project or work package will be done at the same rate of efficiency as the work performed so far.If the cost performance index is greater than 1.0, then


A) the FCAC is greater than the TBC.
B) the FCAC is less than the TBC.
C) the FCAC cannot be calculated with CPI.
D) additional information is needed to predict the FCAC.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions