The ____ for the Entire Project or Each Work Package

Question 9

Multiple Choice

The ____ for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project.


A) total budgeted cost
B) cumulative budgeted cost
C) total cumulative fees
D) contract cumulating amount

Correct Answer: