Multiple Choice
The key to effective cost control is to
A) aggressively address negative cost variances and cost inefficiencies as soon as they are identified.
B) aggressively address positive cost variances and cost inefficiencies as soon as they are identified.
C) extend the project schedule to complete the project in time.
D) all the project to continue and improve.
Correct Answer:

Verified
Correct Answer:
Verified