    Calculate the Earliest Start for Task B If Its Predecessor
Solved

Calculate the Earliest Start for Task B If Its Predecessor

Question 106

Question 106

Multiple Choice

Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.


A) day 5
B) day 3
C) day 1
D) Cannot be calculated based upon information given.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q101: This longest path in the overall network

Q102: The amount of slack should determine the

Q103: The estimated duration for each activity is

Q104: For large projects that involve several hundred

Q105: Total slack for the project is the

Q107: Earliest finish time (EF)is the earliest time

Q108: The total completion time is 25 days.Task

Q109: The estimated resources required for an activity

Q110: Free slack of an activity is<br>A) the

Q111: The project control process must occur regularly

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines