Multiple Choice
Free slack of an activity is
A) the slack on activities that do not have any costs associated with them.
B) can be calculated on every activity with a serial relationship to its successors.
C) the amount of time an activity can be postponed and not delay the start of its immediately succeeding activities.
D) is always a negative value.
Correct Answer:

Verified
Correct Answer:
Verified