Multiple Choice
Positive slack indicates the maximum amount of time
A) that the activities on the critical path should be accelerated to complete the project by the required completion time.
B) that each of the activities in the project can be delayed without jeopardizing completion of the project by the required completion time.
C) that the activities with the positive slack should be accelerated to complete the project by the required completion time.
D) that the activities on a particular path can be delayed without jeopardizing completion of the project by the required completion time.
Correct Answer:

Verified
Correct Answer:
Verified
Q55: As the project progresses, the actual finish
Q56: The sponsor or customer often states the
Q57: An updated project schedule can be generated
Q58: The estimated duration should be aggressive and
Q59: Changes requested early in the project always
Q61: A consistent time base, such as hours
Q62: Each organization or subcontractor responsible for a
Q63: The estimated types and quantities of resources
Q64: The _ and _ times are determined
Q65: The _ and _ times are determined