Multiple Choice
The ____ and ____ times are determined by working through the network diagram from the end of the project to the beginning of the project.
A) ES, EF
B) LF, LS
C) ES, LS
D) EF, LF
Correct Answer:

Verified
Correct Answer:
Verified