Multiple Choice
The ____ of completed activities will determine the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.
A) actual finish times
B) finish estimates
C) actual efficiency ratios
D) actual resource shares
Correct Answer:

Verified
Correct Answer:
Verified