Multiple Choice
Total slack for a project that is negative represents the amount of time that
A) the activities on the path can be delayed and the project still be completed on time
B) all the activities must be accelerated for the project to be completed on time.
C) all the activities can be delayed and the project still be completed on time.
D) the activities on the path must be accelerated for the project to be completed on time.
Correct Answer:

Verified
Correct Answer:
Verified