Multiple Choice
The ____ is a method used to display, in tabular format, the individuals responsible for accomplishing the work items in the WBS.
A) responsibility matrix
B) resource map
C) brainstorm technique
D) task structure
Correct Answer:

Verified
Correct Answer:
Verified