Multiple Choice
The key to quality control is to
A) monitor the quality of the work early and regularly throughout the project.
B) have an external inspector examine the final product only.
C) rework each deliverable to make sure it is right.
D) have extra funds planned into the budget to pay for fast tracking the project.
Correct Answer:

Verified
Correct Answer:
Verified