Multiple Choice
Unlike ____ separate(s) the planning and scheduling functions.
A) the Gantt chart, network techniques
B) the bar chart, the Gantt chart
C) network techniques, the bar chart
D) network techniques, the Gantt chart
Correct Answer:

Verified
Correct Answer:
Verified