A WBS subdivides the project into smaller pieces called ____.


A) object codes
B) task statements
C) work packages
D) work loads

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q83: If the scope seems much less than

Q84: Acceptance criteria for all project deliverables must

Q85: The key to quality control is to

Q86: The WBS usually indicates the organization or

Q87: The work breakdown structure can include specifications

Q89: Multiple individuals should be designated the lead,

Q90: Unlike _ separate(s)the planning and scheduling functions.<br>A)

Q91: The project objective must be clearly defined

Q92: There can be situations where the project

Q93: With the quality plan in place including

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines