Multiple Choice
A task is a piece of work that consumes time.Which statement is false?
A) The duration of the activity is always equal to the total amount of work required to complete the deliverable.
B) Tasks should be subdivided to a level where each task represents a deliverable for the project or the work package.
C) Each activity defines how the work will be done to produce a deliverable.
D) As the project progresses the tasks are further defined and elaborated.
Correct Answer:

Verified
Correct Answer:
Verified
Q95: The project quality plan should state which
Q96: Standard subnetworks should be developed for those
Q97: The network diagram defines the sequence of
Q98: Activities should _ the time intervals at
Q99: List at least three ways information to
Q101: The customer requirements section should also include
Q102: Quality of the project deliverables should be<br>A)
Q103: The success of the project<br>A) is guaranteed
Q104: It is essential to wait until the
Q105: The work breakdown structure is the same