Multiple Choice
The network diagram defines the sequence of how the activities will get done and
A) lists all the activities to be done concurrently in a serial relationship.
B) indicates the loop relationship of the tasks.
C) shows the interrelationships of the tasks.
D) describes the best use of project resources.
Correct Answer:

Verified
Correct Answer:
Verified