    The Optimistic Time Is the Greatest Amount of Time That
Solved

The Optimistic Time Is the Greatest Amount of Time That

Question 123

Question 123

True/False

The optimistic time is the greatest amount of time that could be required to complete an activity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q118: An IT project requires 6 activities.The table

Q119: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3

Q120: Table 11-2<br>The following represents a project with

Q121: Table 11-4<br>The following represents a project with

Q122: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1

Q124: The activity crash cost is equal to

Q125: The activity difference is the actual duration

Q126: Development of a new deluxe version of

Q127: Which of these statements is best?<br>A)Slack is

Q128: The critical path of a network is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines