If an activity's progress is defined as 0% until the moment is complete, the project manager is using:
A) the 50/50 rule.
B) the all or nothing rule.
C) the 0/100 rule.
D) the Do Not Pass Go rule.
Correct Answer:

Verified
Correct Answer:
Verified