Multiple Choice
Each activity contained a series of milestones that represented a previously agreed-upon amount of work.Once the low graffiti was erased,35% of the activity had been completed and once the mid-level graffiti was erased,70% of the activity had been completed.This project manager was clearly in the:
A) percentage complete camp.
B) micromanagement camp.
C) 35/70 camp.
D) 3K specifications camp.
Correct Answer:

Verified
Correct Answer:
Verified
Q50: Once an activity is begun,it is assumed
Q51: Use the S-curve where the solid line
Q52: Earned value management jointly considers the impact
Q53: The first step in earned value management
Q55: At the end of week 10,this project
Q56: You are the new consultant to the
Q57: If the actual cost line on an
Q58: The earned value to date divided by
Q59: Define human factors and discuss their impact
Q87: What are the problems with milestones as