Multiple Choice
All five members of a project team add 10% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 10% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.Much to his surprise,top management cuts only 10% off his time estimate.How much of a cushion is now built into the project?
A) 25%
B) 31%
C) 56%
D) 88%
Correct Answer:

Verified
Correct Answer:
Verified
Q96: A project is represented by the activity
Q97: A worker is assigned three tasks,A,B,and C,each
Q98: The buffers supplied to non-critical paths in
Q99: Describe the Deming funnel exercise and what
Q100: The first step in the TOC (Theory
Q102: An organization's budget estimating process routinely misses
Q103: Delays in project activity are known as
Q104: A project consists of four consecutive tasks
Q105: A project is represented by the activity
Q106: ABC project organization has one workstation that