Multiple Choice
ABC project organization has one workstation that is capable of generating the drawings that their clients study before accepting ABC's bid.ABC is currently in the midst of three proposal projects and knows which proposed project will be most profitable and which will be least profitable.The workstation is scheduled so that the most profitable project's work is done first and the least profitable project work is done last.This is an example of:
A) identifying a constraint.
B) exploiting a constraint.
C) elevating a constraint.
D) subordinating a system.
Correct Answer:

Verified
Correct Answer:
Verified
Q76: Your next project consists of 5 consecutive
Q101: All five members of a project team
Q102: An organization's budget estimating process routinely misses
Q103: Delays in project activity are known as
Q104: A project consists of four consecutive tasks
Q105: A project is represented by the activity
Q107: Create an example and explain how it
Q108: Which of the following statements about CCPM
Q109: The first step in TOC methodology is
Q110: A worker is assigned three tasks,A,B,and C,each