A Project Consists of Six Consecutive Tasks That Have Average

Question 78

Multiple Choice

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project. A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks)  as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.   A)  5 days B)  6 days C)  7 days D)  9 days


A) 5 days
B) 6 days
C) 7 days
D) 9 days