Multiple Choice
A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.
A) 5 days
B) 6 days
C) 7 days
D) 9 days
Correct Answer:

Verified
Correct Answer:
Verified
Q1: All five members of a project team
Q25: Under the student syndrome model,the slope of
Q34: In order to resolve a resource conflict,it
Q39: A(n)_ refers to a safety margin separating
Q50: The _ Theorem states that if a
Q54: _ is variation that is a fact
Q66: Once the organization elevates its constraint,its system
Q82: Project managers often add a(n)_ to individual
Q90: A worker is assigned three tasks,A,B,and C,each
Q110: A worker is assigned three tasks,A,B,and C,each