Multiple Choice
All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 20% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.Much to his surprise,top management cuts only 10% off his time estimate.How much of a cushion is now built into the project?
A) 62%
B) 74%
C) 56%
D) 42%
Correct Answer:

Verified
Correct Answer:
Verified
Q2: A project is represented by the activity
Q3: A(n)_ refers to a safety margin that
Q4: The _ syndrome describes the tendency to
Q5: A worker is assigned three tasks,A,B,and C,each
Q6: A project is represented by the activity
Q7: Which of the following statement is best?<br>A)The
Q8: Drum buffers are:<br>A)a safety margin separating different
Q9: Which of these is Parkinson's Law?<br>A)Don't put
Q10: An important departure from traditional project management
Q11: A project is represented by the activity